SaCeMa Nordic Projects and Rohlig Suus Logistics Collaborate to Relocate One of the Biggest Paper Making Machines in the World

2 min read

SaCeMa Nordic Projects, XLP Member in Denmark, answered the phone call in April and got immediately awarded to relocate “One of the biggest paper making machines in the world, within 8 months”

Predicted contract by customer

Sweden – Poland

1 paper making machine 350 meters x 12 meters x 19 meters / about 8000 ton

300 x trucks IG and OOG up to 1,900 x 350 x 380 cms and up to 108 ton units + 30 x 40’HC SOC.

Started 2 May 2022, Deadline 22 December 2022

SaCeMa Nordic Projects teamed up with fellow XLP Member, Rohlig Suus in Poland, who quickly understood the need, to fulfill commitment, against the customer.

Final Result

Sweden – Poland

1 paper making machine 350 meters x 12 meters x 19 meters / about 8000 ton

480 x trucks IG and OOG up to 1,900 x 350 x 380 cms and up to 108 ton units + 38 x 40’ HC SOC.

Started 2 May 2022, SaCeMa Nordic Projects, finalized 15 December 2022

The project was successfully completed in 7.5 months. Thank you, our great partner Rohlig Suus. The building was handed over to the battery company on 22 December for new adventures.

 

SaCeMa Nordic Projects “The Best Never Rest”

” Denmark – Sweden – Finland – Norway “

Recent Post
Go Gauge Logistics Transports
Heavy Lift Success: Go Gauge Logistics Transports Valves from Italy to India
News
xChange
Container Market Forecaster March 2025
News
Freight Traders Ltd
Freight Traders Ltd Successfully Delivers Key Shipments for New Zealand Power Stations
News

Ready to become a member? Let’s work together

Contact our AiO Logistics Team who will be happy to talk to you!