ScanMarine Estonia OÜ is wrapping up its part in transporting equipment for the Auvere oil plant, “Enefit 280.” The largest part of the work was completed in 2023 when most of the equipment for the oil plant arrived at the Port of Muuga and was transported to the construction site in Auvere.
The widest parts were 5.75 meters in width and 4.95 meters in height.
In this case, the heavy weight was not the issue, but due to the width and height, the transport from Muuga to Auvere had to be carried out at night when there was less traffic on the roads.
ScanMarine were involved in the transportation of equipment produced in Turkey.
A small number of shipments for the Auvere project also came from China. The project started in 2022 and will finish in 2024.
Project Summary:
– Project: Auvere Oil Shale Factory
– Timeline: 2022–2024
– Total Volume: 8,000 m³ / 804 t
Shipments:
LOT 1: APRIL 2022
15 UNITS / 100 t. TOTAL / 1119 m3
CHARTER VESSEL PARTLOAD
BIGGEST ITEMS 13,7 m long / 5,75 m wide / 4,55 m high
LOT 2: MAY 2022
5 x 40’FR / 100 t. TOTAL / 597 m3
BIGGEST ITEMS 4,02 m wide / 4,35 m high
LOT 3: NOV 2022
3 x 40’OPEN TOP + 8 x 40’FR / 150,47 t TOTAL / 1014 m3
BIGGEST ITEMS 4,90 m wide / 4,48 m high
LOT3A: JAN 2023
5 x 40’ OPEN TOP + 12 x 40’FR / 215,97 t TOTAL / 2039 m3
BIGGEST ITEMS 5,65 m wide / 4,10 m high
LOT3B: MAR 2023
5 x 40’FR / 92,98 t TOTAL / 1484 m3
BIGGEST ITEMS 5,65 m wide / 4,95 m high
LOT4.1: MAY 2023
13 x 40’FR / 103,98 t TOTAL / 1074 m3
BIGGEST ITEMS 5,70 m wide / 3,95 m high
LOT4.2: JUN 2023
4 x 40’FR / 40,44 t TOTAL / 673 m3
BIGGEST ITEMS 5,35 m wide / 3,95 m high
PROJECT TOTAL: 8000 m3 / 804 t
Additionally, ScanMarine has delivered numerous LCL and standard FCL cargoes to the production site, with some smaller shipments still expected in 2024.