SaCeMa Nordic Projects Completes Challenging Industrial Relocation of 4000 MT Production Line from Northern Finland

2 min read

SaCeMa Nordic Projects, an XLP member in Denmark, has just concluded work on the industrial relocation of a production line from Northern Finland.

350 x 40’ equipment moved over 8 months, ending off with 3500 m3 Break Bulk loaded onto the vessel during challenging weather conditions in Northern Finland.

The complete production line was safely delivered to a place of receipt in 3rd week of December 2023.

Project Details:

– Relocation / Production Line

– Length: 200 meters

– Width: 6 meters

– Height: 18 meters

– Weight: About 4000 mt

Recent Post
Multimodal
ILG Innovative Logistics Group Delivers 35,000 Freight Tons for a Greenfield Industrial Project in the USA
News
Freight Connection Pakistan
Electrical Transformer & Accessories by Freight Connection Pakistan
News
Megalift Sdn Bhd
Megalift Completes Heavy-Lift Transport of Four Industrial Boilers from Port Klang to Perak
News

Ready to become a member? Let’s work together

Contact our AiO Logistics Team who will be happy to talk to you!