Delivering Power: Total Movements International’s Successful Transport of a 60MW Barge-Mounted Power Plant

2 min read

How did Total Movements achieve this ambitious delivery?
Total Movements International, a proud member of the XLProjects Network (XLP), has once again demonstrated its expertise in project logistics by successfully delivering the Nusantara II 60MW barge-mounted power plant from Surabaya, East Java, to Kolaka, Southeast Sulawesi.

The colossal barge, measuring 72 meters in length, 27.4 meters in width, and 35.3 meters in height, with a total weight of 4,360 tons, was transported seamlessly from the Anchorage Port of Tanjung Perak in Surabaya to the Anchorage Kolaka Jetty in Wolo Smelter CNI Kolaka.

What challenges were overcome during this operation?
Transporting an oversized structure of this scale required meticulous planning, coordination, and execution. Some key aspects of the operation included:

  • Specialized Handling for Massive Dimensions and Weight: The size and weight of the barge necessitated precision handling, specialized equipment, and expert personnel to ensure safe and efficient transportation.
  • Navigating Complex Maritime Routes: Total Movements ensured the vessel’s safe passage across challenging sea routes, with constant monitoring and coordination with local authorities.
  • On-Site Coordination at Both Ports: The operation involved detailed coordination with port authorities at both loading and unloading points, ensuring a smooth transfer of the barge.

Why is this project significant?
The successful delivery of the Nusantara II barge highlights Total Movements’ ability to handle complex and high-stakes projects. By completing the operation with precision and efficiency, the company has reaffirmed its position as a leader in the project logistics sector.

Data Table: Key Details of the Shipment

Item Details
Cargo Description 60MW Barge-Mounted Power Plant
Dimensions (L x W x H) 72 m x 27.4 m x 35.3 m
Total Weight 4,360 tons
Loading Port Anchorage Port of Tanjung Perak, Surabaya
Unloading Port Anchorage Kolaka Jetty, Kolaka, Sulawesi

Summary

Total Movements International has successfully delivered a 60MW barge-mounted power plant, the Nusantara II, from Surabaya to Kolaka. This remarkable feat underscores the company’s expertise in handling oversized and heavy cargo while maintaining efficiency and precision throughout the logistics chain.

Key Takeaways

  • Transported a 60MW barge-mounted power plant weighing 4,360 tons.
  • Seamlessly managed loading, shipping, and unloading operations.
  • Ensured smooth coordination with port authorities and local stakeholders.
  • Demonstrated Total Movements’ ability to handle large-scale project logistics operations.

 

Link Video: https://drive.google.com/file/d/1Fyz_ts8VRAxANzd93DIVaYh15Wp6aTZ5/view?usp=sharing

 

Recent Post
IFT Completes 36,000-Pound Drill Rig Shipment from Maryland to Germany
News
Delivering Power: Total Movements International’s Successful Transport of a 60MW Barge-Mounted Power Plant
News
ESS Projects Successfully Delivers 3,500 FRT Project Cargo from China to Saudi Arabia
Uncategorized

Ready to become a member? Let’s work together

Contact our AiO Logistics Team who will be happy to talk to you!