How did Go Gauge Projects manage this complex shipment?
Go Gauge Projects, a proud member of the XLProjects Network (XLP), showcased its exceptional expertise in project logistics by successfully transporting 29 steel girders from a factory in China to the UAE. Each girder weighed 25 tons and measured 13 meters in length, making this shipment both a logistical challenge and a testament to the company’s capabilities.
The operation had a strict 48-hour EXW (Ex-Works) timeframe, requiring precision, efficiency, and unwavering attention to detail.
What steps were taken to ensure timely delivery?
Go Gauge Projects executed this demanding task by:
- Arranging 29 trailers for the local transport of girders from the factory to the port.
- Conducting customs clearance on a Sunday, ensuring zero delays despite weekend constraints.
- Coordinating the loading of the cargo onto a breakbulk vessel bound for Jebel Ali Port in the UAE.
The seamless execution of this project underscores the company’s commitment to precision and reliability, even when operating under tight deadlines.
Aspect | Details |
Cargo Type | 29 steel girders |
Weight per Girder | 25 tons |
Length per Girder | 13 meters |
Origin | Factory in China |
Destination | Jebel Ali Port, UAE |
Transport Method | Breakbulk shipping |
Scope of Work | Local transport, customs clearance, and loading |
What sets Go Gauge Projects apart?
“From local transport to vessel chartering, we ensure precision and reliability at every stage of the process,”
This successful shipment exemplifies Go Gauge’s ability to handle complex logistics, meet demanding timelines, and maintain safety and quality standards throughout.
Summary
Go Gauge Projects, a member of the XLProjects Network (XLP), completed the seamless transportation of 29 steel girders from China to the UAE under tight deadlines. Their expertise in project logistics, including local transport, customs clearance, and vessel chartering, highlights their commitment to delivering reliable and efficient solutions.
Key Takeaways
- Transported 29 steel girders weighing 25 tons each and measuring 13 meters in length.
- Completed customs clearance on a weekend to avoid delays.
Exemplified precision and reliability under a 48-hour EXW timeframe.